Contents
General
Mission (plenary) sessions
EIS (splinter) sessions
Open Items and Actions
Open Items
New Actions
Closed Actions
List of Materials
Future Activities
General
The planned Japanese solar physics space mission, Solar-B,
was the subject of this "kick-off" meeting, held
at ISAS headquarters in Japan during March 8-13 1999.
This was the first meeting at which all the instrument teams
were present (following the selection of US partners by ISAS,
NASA and PPARC) together with Japanese scientists - from ISAS,
NAO and elsewhere; as well as staff of the main spacecraft integration
contractors.
Each of the three instrument teams held separate meetings.
There were also some joint sessions involving more than one instrument
group and plenary meetings involving all participants.
These notes describe the meetings which involved the EUV Imaging
Spectrometer (EIS) team. Some notes of the plenary sessions are
also included.
Mission (plenary) sessions
EIS (splinter) sessions
Notes.
- criterion for low-maintenance instrument will be included
in Management Plan.
- Noted that since the MTM/TTM testing was reported (by MELCO
engineers) to be essentially in series, the EIS team will aim
to provide test hardware that will satisfy both test requirements.Definition
of Solar-B reference axes will be included in the EIS system
interface control document.
- Noted existence of three documents which comprise the mechanical/structural
interface standards.
- Standards for electrical design currently not available in
English, but expected soon. Astro-E electrical design standards
document will be made available as a guide.
- Noted reference to mathematical model instruction document
per 5.3-3 of s/c overview.
- Information about need for application of contamination control
measures must be conveyed to MELCO.
- Noted data regarding thermal design document.
Mechanical Interfaces
1) It was agreed that the mounting of EIS
to the spacecraft would be with a leg structure, to be provided
by the Solar-B spacecraft (MELCO) side, approximately as shown
in p.'s 5.1-1 & 5.2-5 of the Spacecraft Overview presentation.
Therefore the interface between EIS and the spacecraft will
be between the -y ("bottom") face of the EIS and the
attachment points on the Solar-B structural legs.
There will be no additional legs attached to EIS in the flight
configuration.
2) The EIS instrument will be mechanically qualified,
by BU, (for example by vibration test) with the instrument mounted
on such legs and in the presence of a representative optical
bench portion.
The design may be additionally (or previously) evaluated when
mounted on a fully kinematic mount but this will not constitute
qualification.
3) At flight model, and possibly for other models (TBD), an
exchange of templates between MELCO and BU will be used to control
the mounting interface between EIS and the spacecraft.
4) Adjustment of the EIS alignment will be by shims (for rotation
about the z and x axes) and by pin and slot for rotation about
the y axis, with a TBD fixing method in the latter case.
5) Drawings of the interface will be exchanged. This process
may iterate.
- Action item #46. BU to supply MELCO with a drawing of the immediate
locations of the mounting points on the -y face of EIS.
-
- Action Item #47. MELCO to supply BU with a drawing of the entire leg
structure with all details necessary to permit its dynamical
evaluation.
6) MELCO to provide the EIS team with a preliminary alignment
procedure.
7) BU to provide MELCO with thermal interface information
as requested by 31 March.
8)
- Action # 51.
Mechanism motion characteristics will be supplied (at least in
preliminary form) by end March 99, for frequently used items,
as per the following table:
-
Item |
Mechanism |
Mass |
Torque (Max) |
Duration |
Time-dependence |
Duty Cycle |
1 |
scan of primary Mirror |
|
|
|
|
|
2 |
Slit exchange |
|
|
|
|
|
3 |
slit focus |
|
|
|
|
|
4 |
grating focus |
|
|
|
|
|
5 |
shutter |
|
|
|
|
|
Case studies will be shown in case of uncertainty
in the designs, e.g. what if #5 comprises a filter section. Mechanisms
with an extremely low frequency of use (e.g. door) need not be
shown on this table.
[MW notes: this information will be presented as a section
in an EIS system interface control document]
Discussion on wavelength ranges
...
Electrical Interfaces
- Action 59: MSSL.Need to urgently re-state the EIS team preference
for 28 V unregulated power with justification.
-
- Action 60: MSSL+team.power budget estimates, with average and peak loads.
- A further discussion took place on 15-16 March 99 with (MSSL)
AJM, MW & (NAO) HH, Keiichi Matsuzaki
Here are the notes as taken by Alec:
Requirements Review
Pixel size: 1.9 arc-sec.
Field of view: 4 x 4 arc min.
Spectral Lines:
12 spectral lines should be adequate.
Rasters:
Normally would be sawtooth shape - progressive scan across the
Sun with a fast flyback. An option would be to scan at the same
rate in both directions, and reverse the order of the data in
alternate scans.
Advantages: minimise the disturbance torque.
Disadvantages: possible inconsistent time progression compared
to existing data sets.
Exposure Times:
Quiet Sun: predict about 10s.
Active region: predict about 1s.
Flares: possibly as short as 1ms. First part of flare is the
most interesting.
Automatic Exposure Control (AEC):
Existing (Solar-A SXT) techniques look at the level of flux
present two exposures before the current one to determine an
auto exposure factor. An alternative approach is to look at the
target a very short time before the required exposure - say 500ms
before. To minimise the CCD readout time for the metering, one
or two key lines could be chosen which are known to be active
during flares. There is no need for the wells of the CCD to be
more than partially full, in order to keep the metering time
short, as maybe 20% accuracy is adequate. The sequence for AEC
then becomes:
Command to take exposure
Short metering exposure
Read two metering lines from CCD (no download to MDP)
Calculate AEC factor in EIS
Take real exposure using this AEC factor.
Process data in EIS
Download to MDP
Typical Data Rates:
SOT: 1 M pix per sec (~ 8 M bit per sec ?)
XRT: 500 k pix per sec (~ 4 M bit per sec ?)
EIS: 1 M bit per sec
Likely cable run for EIS is 5m.
(AJM: This is a significant length for data transmission and
supply voltage losses. It definitely implies supply regulation
in the camera head)
There was a mantra repeated several times: CADENCE,
CADENCE, CADENCE. Throughput is everything.
If EIS carries out the data compression, it should include
simple bit compression as one of a selection.
Mission Data Processor
This will be designed by NAOJ (KM) and built to contract. It
connects the science and command channels of the three instruments
to the spacecraft. For SOT? (XRT?) it provides all the processing
power. Probably based on Thomson-CSF PowerPC 603e good to 60krad
total dose.
CCD Readout & Digitising
Above 20 - 50kHz readout rate, noise increases with frequency.
It might be possible to optimise the readout rate in a continuous
manner with every exposure to give the lowest noise level.
Timeline
Setup ------ ------
Flush --- ---
Exposure ------
Readout ---
MDP Output Rate to Data Recorder
64kbit per sec average. Critical figure is 1 or 2 Mbit (TBD)
per sec peak. We need to engineer the system, including the MDP,
so that EIS (or any instrument) can take the full data stream
for itself in case of other instruments being non-operational.
Should physical maximum data rate of EIS be ~12Mbit per sec?
(for drivers and cable)
Need a way for EIS to estimate the data volume left at any
point. Do this by MDP informing EIS at the start of the day of
the available data space, and counting the data volume sent?
Mission Uplink
Very small data size, maybe three times Yohkoh (how much?). NAOJ
to find value. Data corrected for tranmission errors (what bit
error rate achievable?). Patches must be small!
Some commands need tagging in their database as hazardous. Obvious
examples are the door open and launch lock release.
Observing Tables
An important requirement for these is to minimise the data upload,
probably with a system of pointers to tables already loaded in
EIS. Necessary parameters include:
Exposure duration
Window
Scan mode
AEC parameter
AEC enable / disable
Dark / non-dark (?)
Binning
Slit
Compression
We should look at the use of SOHO-CDS to see what can be learnt.
For Solar-A SXT, the major problem is that there is no timeline.
EIS could also use a macro command structure, run with a parallel
timeline to the observing tables timeline.
EIS Thermal Control
The spacecraft will be responsible for thermal control and monitoring
of EIS. There are maybe ten channels for control and monitoring.
Need to understand to what precision the spacecraft can control
(NAOJ) and how many channels might be necessary with their requirements
(BU).
Non-operational mode monitors
The door and launch lock status, and possibly other mechanisms,
will require monitoring with EIS unpowered. This interface needs
to be defined.
Science and HK Packet Size
Need to suggest maximum packet size - 10kbit first estimate.
Is a compromise between too small giving a proportionally large
overhead of framing data, and too large giving long retransmit
times in the case of data downlink dropout.
Estimated 20 packet per sec from MDP to DHU (data handling unit)
using CCSDS format. EIS should use the same format if possible.
Packets are fixed length header with variable length data, maximum
length not defined.
Main Bus Power
Voltage not defined, but all three experiments prefer 28V. Inrush
current, EMC levels, and most other parameters are not defined
yet. 31 March meeting with MELCO will be important for this.
Provide initial power budget with error bars for this meeting.
ASTRO-E documents may help - Hara san to check.
Shutter mechanism is likely to require 3W - same design as
SOHO MDI.
Design Principle
A long discussion on user interaction produced the following
concept:
The system should be designed to be easy to use from a science
user point of view, and should not inhibit any commands unless
defined as hazardous.
EGSE
Nothing defined - CCSDS information will be basis for the format.
-------------------
Actions (MSSL)
Information requested from NAOJ:
- 61.
What precision
of temperature control can the spacecraft provide for thermal
nodes on the EIS?
-
- 62.
Define interface
between non-operational mechanisms and spacecraft.
-
- 63.
Peak data rate
from MDP to Data Recorder for EIS.
64. (requested by MSSL) Total
peak data rate from MDP to Data Recorder for all three instruments
together.
65. Define general format and
in particular the maximum length of packet from the MDP to DHU
to allow EIS to consider use of the same format.
66.
Outline concept
of the interface between the Solar-B ground system and the EIS
egse.
|
Open Items and Actions
Open Items
...
New Actions Arising
(action numbers continue from previous EIS consortium meetings)
46. BU - Supply MELCO (via H. Hara) a drawing of the spacecraft
interface points on the -y face of EIS.
47. MELCO - Provide drawings and descriptions of the semi-kinematic
attachment structure for EIS.
48. MELCO. Produce a preliminary alignment procedure
49. BU. Provide MELCO with thermal interface information as
requested. 31/3.
50. NRL/MSSL. Mechanism motion characteristics table to MELCO.
51. All EIS team institutes. Provide data of materials proposed
for use in, or in the vicinity of, the instrument optical components.
52. MSSL to coordinate update of mass and power budgets.
53. All. Select wavelength ranges.
54. All. State scientific objectives and requirements.
55. MSSL. Provide a statement of the need for contamination
control hardware on the spacecraft (i.e. purge harness) on the
spacecraft and up to launch.
56. hh/jd. Continue to develop and report the Hitachi-ruled
SVLS gratings.
57. jd. Provide some SERTS spectra to MSSL for instrument
(CCD) simulation and development.
58. BU/NRL. Implement a test programme of Cycom 5575 and/or
other carbon-composite materials with appropriate multilayer
coated witness samples.
59. MSSL: state main bus power preference
60. MSSL/team: power consumption estimates
61. MSSL/team: spacecraft heater/sensor requirements
62. MSSL/team: non-operational status items
63. MSSL: EIS peak data output rate
64. NAO: MDP/DR peak data input capacity
65. MSSL: EIS packet format
66. MSSL: ground system/EGSE interface concept.
Closed Actions from previous meetings
List of Materials
Session
p=plenary
e=EIS
x=XRT |
Title
(or Theme) |
Pages
[slides] |
Author
or (Presenter) |
Reference
(MWT's system) |
p |
Agenda |
11 |
Kosugi |
ko/m/0-2 |
|
List of Foreign Participants |
1 |
Kosugi |
ko/m/0-1 |
|
International cooperation in the Yokhoh Programme |
8 |
Kosugi |
ko/m/2 |
|
(Scientific Objectives etc.) |
4 |
Kosugi |
ko/m/1 |
|
Master Schedule |
1 |
Kosugi |
ko/m/4 |
|
Spacecraft Overview - SLB-M-E-99002 |
43 |
MELCO |
ko/m/3 |
|
Electrical Interfaces |
1 |
MELCO |
ko/m/3-1 |
|
Requirements for structural mathematical models |
8 |
MELCO |
ko/m/10 |
|
Mechanical Design Standards |
13 |
MELCO |
ko/m/11 |
|
Contamination Control Program Plan |
5 |
MELCO |
ko/m/9 |
|
Environmental Conditions for Solar-B |
18 |
MELCO |
ko/m/8 |
|
|
|
|
|
|
Telemetry and Commands |
8 |
Sakao |
ko/m/5 |
|
Attitude Control Systen |
[16] |
Ichimoto |
ko/m/6 |
|
Data Coalignment Concept --> MDP -> Operations |
10 |
Shimizu |
ko/m/7 |
|
|
|
|
|
e |
Observations with Baseline EIS |
|
Hara |
ko/e/1 |
|
Thoughts on reaching closure ... |
|
Mariska |
ko/e/2 |
|
EIS Structural Analysis |
|
Mahmoud |
ko/e/3 |
|
|
|
|
|
x |
XRT Mirror and Filter Performance |
35 [69] |
deLuca |
ko/x/1 |
|
XRT Analysis Filters |
[~16] |
Kano |
ko/x/2 |
|
XRT Engineering Presentation |
36 |
Cheimets |
ko/x/5 |
|
CCD Charge spreading |
9 |
(Bruner) |
ko/x/3 |
|
CCD test for device selection |
[14] |
Kano |
ko/x/4 |
Future Activities
|