Solar
B - EIS
RUTHERFORD
APPLETON
LABORATORY
|
Author: B J Kent
|
CLEANLINESS CONTROL
PLAN
Document Number: MSSL/SLB-EIS/PA/003.01 22 June
2000
Distribution:
NRL
|
G Doschek
|
|
|
C Korendyke
|
|
|
S Myers
|
|
|
C Brown
|
|
|
K Dere
|
|
|
J Mariska
|
|
|
|
|
NAOJ
|
H Hara
|
|
|
T Watanabe
|
|
|
|
|
RAL
|
J Lang
|
|
|
B Kent
|
Orig
|
|
D Pike
|
|
BU
|
C Castelli
|
|
|
S Mahmoud
|
|
|
|
|
Mullard Space Science Laboratory
|
J L Culhane
|
|
|
A Smith
|
|
|
A James
|
|
|
L Harra
|
.
|
|
A McCalden
|
|
|
C McFee
|
|
|
R Chaudery
|
|
|
P Thomas
|
|
|
R Card
|
|
|
W Oliver
|
|
|
P Coker
|
|
|
R Gowen
|
|
|
K Al Janabi
|
|
|
M Whillock
|
|
SLB-EIS Project Office
|
A Dibbens
|
|
Author:
|
B J Kent
|
Date:
|
22 June 2000
|
|
|
|
|
Authorised By
|
|
Date:
|
|
|
|
|
|
Distributed:
|
|
Date:
|
|
CHANGE RECORD
ISSUE
|
DATE
|
PAGES CHANGED
|
COMMENTS
|
01
|
22 June 2000
|
All New
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page:
CONTENTS
1. Scope and Relationship to other Documents
This document addresses the necessary contamination control activities
required to maintain the scientific performance of the EIS instrument. It
provides background information on contamination control, summarised in 'Golden
rules for Contamination Control' in Appendix 3 and specific information in
section 7 on the preparation and handling of EIS components.
This
document is related to and subservient to the Spacecraft Contamination Control
Plan (reference TBA) and is higher level than the NRL Document EIS_CC_Plan
(April 2000). In issues of the authority the hierarchy is spacecraft - first,
instrument- second, optics last.
2. INTRODUCTION
The objective of this document is to establish contamination control
requirements and define their implementation in order to assure EIS instrument
performance objectives are met through to the end-of-mission life. The EIS
contamination control plan identifies, allocates, and budgets EIS instrument
contamination limits and requirements to meet instrument performance
specifications. This document develops plans and implementation procedures to
assure EIS instrument performance at end of mission life shall not be
unacceptably degraded due to contamination. It is anticipated that this
document be modified and amended to follow the development of the EIS
instrument.
The document is based on templates produced for the SOHO CDS
and the XMM OM but with an evaluation of the particular requirements for the EIS
instrument. The cleanliness requirements for the EIS instrument are
challenging.
We have assumed the NRL levels defined for
optics in EIS_CC_Plan which are that the end of life molecular
contamination shall be <
10-7 g
cm2 and that the particulate contamination shall be
<150 ppm. These requirements are demanding
and essential for the unit to reach its full sensitivity and great emphasis will
be placed on achieving them.Both molecular and particulate
contamination is of concern for EIS. Molecular contaminants degrade the
instrument sensitivity by a general attenuation which can be exacerbated at
individual wavelengths by specific absorption of particular materials e.g.
silicones. Particulate contamination contributes a scattered background, which
reduces image contrast.
Molecular and particulate contamination will be
monitored. In order to minimise the effect of molecular contaminants, careful
choice of materials must be exercised both in the EIS instrument and the clean
room environment in which it is assembled. Close attention must be paid to
out-gassing paths and cleanliness procedures during storage, integration,
transport and before launch. Small witness optics will be placed near sensitive
optical elements e.g. the mirror and grating, two per position. One will be
capable of being removed periodically to evaluate intermediate contamination
levels, whilst the other will be left to determine total dose up to delivery.
Infrared spectroscopy will be used to measure molecular contamination.
Particulate contamination can be readily controlled by the use of
well-managed clean rooms. Experience with other experiments, e.g. CDS, has
shown that when stringent controls are in place and clean room activity is well
policed, particulate contamination problems can be avoided. Additional
requirements and procedures may be introduced during the course of the design,
development and fabrication of the experiment, as and when the need is
identified.
Contamination Control requirements apply to flight
hardware, to operations with and including flight hardware, and to instruments,
equipment, facilities, tools, processes and materials used with, and in, EIS
flight hardware.
3. APPLICABLE DOCUMENTS
NRL_EIS_CC_Plan CCIP, EIS Instrument Components, NRL, April
2000
FED-STD-209B Clean Room and Work Station Requirements, Controlled
Environment
MIL-STD-1246A Product Cleanliness Levels and Contamination
Control Program
ESA-PSS-01-201 Contamination and Cleanliness
Control
ESA-PSS-01-204 Particulate Contamination Control in Clean Rooms by
Particulate Fallout (PFO) Measurements
ESA-PSS-01-705 The Detection of
Organic Contamination of Surfaces by Infra-Red
Spectroscopy
PL/TN/819/RT/870 SOHO Preferred Materials
Document
PL/TN/820/RT/870 SOHO Outgassing
Data
4. CONTAMINATION SOURCES - OVERVIEW
Contamination is conveniently described as either
particulate - small discrete masses of solid or liquid matter,
usually measured in terms of particle size (in µm) or
molecular - such as water and thin film deposits on surfaces from
condensed volatile organic and inorganic materials caused by contact or gaseous
transfer and is measured in terms of layer thickness (e.g. ?) or specific area
(e.g. g cm
-2).
Sources of contamination are many, and occur at all
phases of a programme beginning with component fabrication continuing through
end of mission life on orbit. Minimising the effect of these sources is the
prime purpose of this plan and specific implementation procedures are contained
in the section on EIS Components Specifics (section 7) and the cleaning
schedules in Appendix 2.
Some sources of particulate contaminants are as
follows:
• Particles and non-volatile residues remaining from
machining, painting and other fabrication and assembly processes which may be
transferred by contact or other means.
• Airborne particles, skin
flakes, hair fragments, wear-generated material from clothing and other human
detritus.
• Airborne particle fallout within ground-operation
environments due to turbulent air, unfiltered atmospheric air, and/or pump-down
and
re-pressurisation turbulence during vacuum chamber
operations.• Paint flakes, metal particles, and other forms
released or generated by hardware or GSE.
• Transfer of particles from
adjacent surfaces during sub-system, instrument, and / or spacecraft vibration,
shake, acoustic, and/or shock testing.
• Particles in the payload
fairing and acoustic blanketing of the launch vehicle that are loosened and
re-distributed during ground operations and launch.
• Particles
dispersed by the effects of mechanical shock due to the opening and jettisoning
of launch vehicle nose-fairing.
• Trapped particles on or in the
experiment package that are released and redistributed during ground operations
and launch, including deployment of solar arrays, release of hold-down
mechanisms and deployment of aperture doors.
• Contamination from the
spacecraft and other payloads.
• Space-borne particles,
micrometeoroids, and debris.
Some sources of molecular contaminants are
as follows:
• Lubricants, fluid leaks, and exposed organic
materials, which permit molecular components to be contact-transferred to
critical surfaces during hardware handling.
• Cryodeposition of gaseous
materials and organic or inorganic material arising from offgassing or
outgassing during thermal vacuum testing, other vacuum operations, and/or
on-orbit operations.
• Molecular cloud environment
generated by operations and out-gassing of launch vehicle surfaces and motors,
spacecraft surfaces and thrusters, and payloads which may condense on cooler
(not necessarily cryogenic) surfaces.
• Return flux of out-gassed
molecules caused by collisions with residual atmospheric molecules and
self-collisions.
• Off gassing of plasticers and other organic
volatiles from the assembly/test environment (e.g. clean room
materials).
5. CLEANLINESS REQUIREMENTS SPECIFICATION
5.1 Component Parts
The EIS instrument is one of four instruments on the Solar B spacecraft.
The EIS Instrument consists of:
- The optical assembly support structure and
enclosure
• Composite honeycomb
structure with composite face panels
- An optical assembly (telescope/spectrometer) containing the following active
parts
• Filter and filter door
mechanisms
• Off-axis paraboloid,
multilayer telescope primary mirror
• Mirror
focus mechanism
• Slit-slot mechanism with
shutter
• Slit-slot filter
• Spectrometer grating with multilayer
coating
- Grating mount assembly
- Grating focus
mechanism
• Focal plane assembly
with CCD detector
- Electronic Units
containing:
• Digital instrument
control and data processing
electronics
• Analogue
electronics
• Power supply
electronics
- Interconnecting harness units
- Radiator with thermal link to CCD
- Thermal blanket
The components described in section b
above are subject to contamination control as specified in the NRL document
EIS_CC_Plan, in addition to this
document.
Multilayer
insulation (schematic) (Source and sink)
Detector radiator (cold –
sink)
Graphite Cyanate Ester composite
(source)
Filter
(sink) and filter door mechanism (source)
Primary Mirror (sink) with
focus mechanism (source)
Entrance beam
Grating (sink) with
focus mechanism (source)
Detector radiator
(cold -
sink)
Entrance
slit (sink) and shutter mechanism (source)
Detector (cold - sink)
Figure 1
Figures 1 shows sketches of the
instrument configuration in perspective and plan views to illustrate the number
and location of component parts and their contribution (source or sink) to the
contamination budget.
5.2 Critical/ Sensitive Parts
Critical components are those whose performance is compromised by either
molecular or particulate contamination. Such a description is obviously
appropriate for optics, both for molecular and particulate contamination of
surfaces and particulate obstruction of small apertures (e.g. spectrometer or
optical encoder slits) but it is also applicable to thermal control hardware in
which surface properties play a significant role. Critical components are also
those which are colder than their surrounds and thus act as a ´sink' for
molecular contamination. When cold items are also optically sensitive such as
the EIS cooled CCD detector extreme caution must be exercised in maintaining a
clean environment.
The critical optical parts of EIS are the telescope,
grating and detector, listed in the optical assembly above. These are central
to the performance and overall sensitivity of the instrument.
The
remaining parts are less sensitive to contamination, but may themselves be
contamination producers. Steps to reduce and control these effects will be
specified later in this document.
5.3 Degree of Sensitivity of Critical Parts
Information on the criticality and sensitivity to molecular and particulate
contamination for various parts of the instrument will be established.
This
information shall be broken down to the following
stages:-
• End of mission
• Post launch (start of
mission)
• Pre-launch
• Spacecraft
integration and environmental
test
• Instrument
storage
• Transportation
• Assembly,
integration and verification, including radiometric
calibration
• Subsystem
storage
• Optics manufacture
To do
this, it will be necessary to calculate the effect of specific deposits of
particles and condensed organic material on each of the susceptible
elements.
We assume that end of life performance degradation must be no
greater than 20% in the EIS wavelength range of 180 Å to 290 Å and
estimate that this requires molecular contamination to be
<10
-7 g cm
-2 at end of life.
For
particulate contamination, the end of life figure shall be 300 ppm, assuming a
distribution figure as specified in Mil Std 1246A. See figure
2.
Figure
2. The plot shows the time measured in days (horizontal axis) for surfaces
exposed in clean rooms of various air class defined by FED-209C (the curves for
these are labeled on the right) to reach a surface cleanliness level as defined
by MIL-STD-1246 (vertical axis).
The overall contamination accumulated by
EIS during its entire life from assembly, through test and final operational
phase can be allocated to each of these phases as shown in the following chart
which indicates both molecular and particulate cleanliness budgets. Arbitrarily
we have assumed that 60% of the molecular contamination will occur post launch.
For particulates we have assumed 50% of contamination occurs post launch with
25% of that occurring during the immediate post launch phase.
|
Budget
|
|
Molecular
|
Particulate
|
|
% Allocation
|
Accumulated Level (gm cm-2)
|
% Allocation
|
Accumulated Level (ppm)
|
Post clean
|
|
< 1 x 10-8
|
|
<40
|
Modules pre-integration
|
10
|
2 x 10-8
|
20
|
50
|
Storage /transportation
|
0
|
2 x 10-8
|
0
|
50
|
Instrument integration
|
10
|
3 x 10-8
|
15
|
60
|
Storage /transportation
|
0
|
3 x 10-8
|
0
|
60
|
Spacecraft integration
|
20
|
4 x 10-8
|
20
|
75
|
Pre-launch
|
10
|
5 x 10-8
|
10
|
85
|
Post launch/pre ops
|
30
|
7 x 10-8
|
25
|
110
|
Scientific operations
|
30
|
10-7
|
25
|
150
|
Total - End of Mission
|
100
|
10-7
|
100
|
150
|
5.4 Sources of Contamination
Known and/or expected sources of both molecular and particular contaminates
must be identified in order that appropriate steps can be taken to minimize
their effects.
Sources of particulate contamination
include:
Mechanisms
Especially those mechanisms listed in the optical
assembly and indicated in figure 1.
Poorly finished fibrous material
We
must be concerned over the composite material honeycomb face plate
edges.
Residual debris from machining
Trapped debris in composite material
honeycomb.
Purge /flush gas
Use of filtered high quality purge gas (at
least white spot) is mandatory.
Redistribution
processes
Handling
Pump down to vacuum
Recovery to atmospheric
pressure
Sources of molecular contamination include:
Lubricants
Surface treatments e.g. paints
Residue from cleaning
process
Re-condensed products form exterior sources e.g. clean room
walls/floors/filters
We must expect significant out-gassing of water
vapor from the honeycomb structure and anticipated that even after a high
temperature air bake the initial pump will be of long duration (perhaps a few
days).
Details of the materials used in the experimental hardware will be
listed in the Declared Materials List (reference TBD).
An analysis of the
temperatures, mass and exposed areas of all potential out-gassing sources must
be made. Knowledge of vent conductance and quantification of out-gassing data
versus time and temperature will aid contamination estimation. If there is any
possibility of particle generation by the equipment, then estimates of it should
be made, e.g. thermal insulation, swarf, abrasion during vibration etc.
A
list of processes used in the manufacture of the experiment will also be
prepared as the Declared Processes List (reference
TBD).
6. CLEANLINESS CONTROLS
6.1 Design
6.1.1 Design for Cleanliness
The design shall as far as possible separate contamination sources from
contamination sensitive critical items. Ideally this would mean placing all
optics in a separate enclosure from mechanisms and potential out-gassing
sources. In EIS this ideal is not possible and both mechanisms and potential
out-gassing graphite composites are part of the optical volume. Sources of
molecular contamination shall be remote from 'cold sinks' and where this is not
possible sources shall be cleaned to levels such that their out-gassing is
compatible with required instrument performance.
Materials shall be
selected bearing in mind the contamination potential in the use location. In
critical areas only materials of known low rates of out-gassing shall be chosen.
It may be
necessary to use adhesives, surface coatings and
exceptionally potting materials, but the use of such materials will be
controlled and approved by the contamination control engineer.
In general
materials must be selected from a recommended lists e.g. ESA PL/TN/819/RT/870
and PL/TN/820/RT/870. However, experience has shown that for EUV instruments
additional material screening is needed to preserve out-gas requirements e.g.
testing by ESA's Vacuum Balance Quartz Crystal (VBQC) test.
Optical
components and their mounting structures should be covered when access is not
required.
The design shall ensure that critical areas may be protected e.g.
by covers during periods when access is not needed. When access to critical
components is required the design shall ensure that such items may be worked on
such that workers do not contaminate the component e.g. in a clean room with
workers downstream of the component.
6.1.2 Clean Rooms Facilities and Clothing
For particle control, clean-rooms/benches must be used appropriate to the
cleanliness needed. The optics must see class 100 or better. The doubly bagged
instrument may be exposed to class 100000. Clean room clothing, work practices
and discipline must be adopted according to the procedures agreed in each case
with the EIS system team.
In general clean room work is uncomfortable and
the discipline exasperating, hence such work needs to have well planned specific
objectives which take the minimum careful time and with time allowed to return
work items to safe, clean configurations following clean room
operations.
The particulate sensitive assembly work for EIS will take
place in class 100 category clean rooms. CDS experience indicates that class 100
conditions are not possible unless scrupulous control is maintained over clean
room practice.
The number of staff in the clean room shall be restricted to
that number which does not compromise the class 100 conditions. As an
approximate guide RAL SSTD experience is to limit staff to 1 person per 10
m3.
Class 100 clothing shall consist of:
- Full coverall suit
- Head covering of full cowl type
- Face mask covering nose and mouth
- Class 100 powder free gloves
- Mid calf length boots
6.1.3 Purging
Critical volumes shall be purged with clean dry inert gas (at least white
spot quality) distributed through clean delivery lines. It is essential to
design the internal flow of this gas so that it passes first over the most
critical surfaces and that no critical surface is purged by second-hand gas. It
may also be important, from the point of view of neighboring sensors, that the
purge gas be vented in a controlled manner.
Note the potential safety
problem of asphyxiation if purge rate is large compared to the clean room
refresh rate.
6.1.4 Contamination Traps
The design should avoid the creation of traps for particles during
manufacture and/or assembly.
The use of honeycomb structure presents a
particular problem, as this material comprises a large number of particle traps.
It must thus be sealed to prevent particle entry to the optics volume. The
outermost surface cover should be perforated to allow the honeycomb to out-gas
through the outermost face.
6.1.5 Access for Cleaning
Consideration shall be given to all critical items to allow for the ability
to clean them at the latest possible stage in the final assembly process.
The use of removable covers for these devices will provide protection during
storage and transportation and 'waiting for work' periods. They should provide
snug but not necessarily airtight seal and be made from non-plasticised
material.
6.2 Manufacture, Assembly and Test
6.2.1 Manufacturing Controls
It is essential that good design is not compromised by poor
practices.
Cleaning of any part after machining must involve coarse cleaning
using ultrasonic or solvent vapor dip before leaving the workshop
area.
Before entry to any clean room, the hardware must undergo precision
cleaning.
Suitable cleaning schedules covering instrument parts and support
systems are attached as Appendix 2.
Analytical grade solvents, stored in
glass containers, are required for this purpose.
Tools and MGSE/EGSE used in
clean-rooms must be precision cleaned before clean room entry. GSE must never
be used upstream of flight hardware.
All clean rooms re-circulate a large
proportion of the air. The standard filters used are designed only to trap
dust. If there is a risk of chemical contamination, then the use of active
carbon filters should be considered and molecular contamination levels monitored
in any case.
6.2.2 Processes
Processes are also critical, since errors in the preparation or application
of potting materials, adhesives and paints may destroy the EUV performance of
optical surfaces and there use must be strictly controlled. It is considered
essential to validate the choice of such materials by producing test samples,
representative in size, shape and materials, prior to the application to flight
hardware to confirm freedom from out-gassing in its expected life profile.
If
potting is used as a technique, the flight hardware should be vacuum baked
before the next assembly, providing that this will not cause any performance
deterioration. The bake should be monitored to demonstrate cleanliness, as this
will reveal incorrect or incomplete curing of the potting compound. Similar
tests should be conducted for paints and the results of all these tests shall be
recorded in the equipment logbook.
6.2.3 Inspection
Verification of cleanliness before fitting any assembly or closing any
panel or cover is required. This will be aided by inspection with UV light,
which shows organic contamination by fluorescence and by a strong beam of white
light arranged to graze the ostensibly clean surfaces. The white light is best
for inorganic materials and so is complementary to the UV.
A further method
of verification is the tape lift test, in which a special adhesive transparent
tape designed for the purpose is applied to typical areas, removed and inspected
under a microscope to quantify any particles present. This technique is not
applicable to optical surfaces, and only to other parts with agreement of the
contamination control engineer.
After piece part manufacture, all components
must be precision cleaned before entry into the clean room or before being
placed into part storage. If storage is prolonged, then the need for repeated
precision cleaning operation should be evaluated before the next assembly
operation.
6.2.4 Monitoring
Monitoring the cleanliness of the assembly operations is mandatory. The
use of witness plates, as described in ESA PSS-10-201, is recommended throughout
all assembly or handling operations involving critically clean hardware. ESA
specifications PSS-01-201, -204 and -705 give more details of particle and
condensable monitoring. (Test specification to be
verified.)
It is recommended that clean benches be
"qualified" before use by exposing witness plates for 2 weeks or so prior to
use. When the bench is operating witness plates will be used to verify no
recorded detectable contamination. Results of these tests shall be kept in the
equipment logbook.
6.2.5 Removal of Particles
For non-critical surfaces, light brushing with airflow into a vacuum nozzle
is usually effective and is best carried out with the lighting described in par
6.2.3. The judicious (approved) use of tape lifting as described in par 6.2.3
may be appropriate for removal of a limited number of particles where the
introduction of a vacuum hose is difficult. Note that high gas flow rates may
introduce electrostatic charging problems, which apart from risks of damage to
ESD sensitive components may simply attract particles to the charged surfaces.
To avoid this problem, use low flow rates and de-ionized gases.
By strict
adherence to the cleaning and handling instructions there should be no need to
attempt removal of particles from optically critical surfaces. However in the
need for accident recovery, particles may be removed from optical surfaces with
the greatest of care by non-contact methods such as vacuum induced airflow.
With care this may be supplemented by a jet of clean de-ionized nitrogen
directed to dislodge the particle so that the gas with the freed particle is
then removed via the vacuum pipe. On no account should pressurised cans of air
or photographers 'puffer' bulbs be used. Particle removal from thin film
filters must never be attempted.
6.2.6 Vacuum Bake-out
The removal of molecular contamination shall be carried out using a vacuum
bake-out.
Items should be vacuum baked prior to assembly, using a temperature
compatible with the items’ materials; for example aluminum approximately
150
° C, wiring harnesses approximately
80
° C. The duration of the vacuum bake-out
shall be as described in Appendix 2 schedules as a minimum, and this could be
longer depending on the out-gassing rate of the item. The chamber pressure
during bake-out shall be as described in Appendix 2. A further vacuum bake-out
of the assembled instrument is recommended. The temperature for this bake-out
shall be no greater than the lowest temperature used during individual item
bake-out.
6.2.7 Storage
Packing or temporary storage of piece parts and equipment requires some
extra precautions to preserve cleanliness after any precision cleaning
operation. For small metal parts and assemblies, it is recommended that clean
aluminium foil be used as the primary packing material. The wrapped item is
then sealed inside a suitable non out-gassing plastic bag such as Llumalloy,
aluminized Kapton or Mylar. Larger items should be sealed in Llumalloy
bags.
Humidity 'tell tales' and shock indicators may then also be
enclosed.
Optics should be stored in a sealed metal or project approved
container filled with dry inert gas.
The hardware can then be transported as
required from the clean room, but must not enter another clean room in this
level of packaging. Following normal practice, the outer container must be
cleaned before entry into a semi-clean-room area and opened to remove the
treble-wrapped hardware. The wrapping is removed progressively as the hardware
moves upstream towards the workstation allocated for the next operation and the
final aluminium foil wrap must only be removed at the clean bench. No plastic
material must ever reach the clean bench or inspection area.
Major
subassemblies and/or the complete instrument may be stored in sealed containers
that are capable of being purged with clean dry inert gas.
6.2.8 Thermal Vacuum Testing
Before testing of the complete experiment, it will be necessary to certify
that the test chamber is adequately clean.
- Prior to the testing of any flight or flight spare hardware, the cleanliness
of the chamber must be certified in the course of a thermal vacuum test similar
in duration and temperature
extremes planned for EIS.
The MGSE must be similarly cleaned as must any other test hardware as specified
in Appendix 2. Quartz Crystal Monitors (QCM's) and witness plates/foils should
be fitted to demonstrate the capability of the chamber to meet the required
cleanliness levels.
- The duration of this vacuum test is unlikely to be less than 48 hours,
except for small chambers, but should be determined by measuring the out-gassing
rate. This should be less than 10- 7g/cm2/hr (TBC).
At the end of this test, the witness samples and surface wipes shall be measured
for contamination to confirm that the chamber is clean enough for the EIS
hardware. In the interval between the bake-out and the real test, it is
recommended that the chamber is back filled with dry nitrogen and
closed.
c) Recovery from thermal vacuum should take place
after the chamber has returned to room temperature following a hot cycle. Clean
high quality nitrogen (
TBD specification) shall be
used to purge the vacuum chamber after first passing through the instrument,
i.e. the chamber is refilled via the EIS instrument until a pressure of 1 torr.
At 1 torr the chamber may be pressurized in parallel with EIS provided
structurally harmful pressure differentials are avoided.
6.2.9 Using Vacuum Chambers (apart from thermal vacuum)
Before testing in vacuum of the complete experiment, it will be necessary
to certify that the vacuum chamber is adequately clean.
a) Prior to the
vacuum testing of any flight or flight spare hardware, the cleanliness of the
vacuum chamber must be certified in the course of a vacuum test similar in
duration and temperature to that planned for EIS. The MGSE must be similarly
cleaned as must any other test hardware as specified in Appendix 2. Quartz
Crystal Monitors (QCM's) and witness plates/foils should be fitted to
demonstrate the capability of the chamber to meet the required cleanliness
levels.
b) The duration of this bake-out is unlikely to be less than 48
hours, except for small chambers, but should be determined by measuring the
out-gassing rate. This should be less than
10
-7g/cm
2/hr (TBC). At the end of this test, the
witness samples and surface wipes shall be measured for contamination to confirm
that the chamber is clean enough for the EIS hardware. In the interval between
the test and the real test, it is recommended that the chamber is back filled
with dry nitrogen and closed.
c) Recovery from vacuum should take place
by using clean high quality nitrogen (
TBD
specification) to purge the vacuum chamber after first passing through
the instrument, i.e. the chamber is refilled via the EIS instrument until a
pressure of 1 torr. At 1 torr the chamber may be pressurised in parallel with
EIS provided structurally harmful pressure differentials are avoided.
6.2.10 Hardware Handling
At all times the minimum number of technicians and inspectors will be used
to work on and handle the flight and flight spare hardware. (See also section
6.1.2.)
6.2.11 Logbook Records
Records must be kept in a logbook forming a chronological listing of the
events possibly affecting the cleanliness of the flight or flight spare
hardware. The contents of this logbook, or section of the Experiment's logbook,
will contain:-
- the as built materials list
- process data, e.g. material batch numbers, time of mixing, application, cure
and test sample data
- time/temperature summaries for the bake-out
- QCM, witness plate and wipe data relating to the assembly or test operation
involved, including those applicable to a "blank test" of thermal vacuum
chambers
- a time log of gas purging, where applicable
- certification at the time of delivery of the hardware, that the cleanliness
records have been reviewed, are complete, correct and satisfactory. This
certification is required prior to acceptance for the next level of
integration
7. EIS COMPONENT SPECIFICATIONS
7.1 The optical assembly support structure and enclosure
1) Structure:
SWALES experience on FUSE suggests the following cleaning
requirements for carbon composite structures:
Bake in air at
120
° C for 5 days
Vacuum bake at
100
° C until pressure is in low 10
-6
torr range and partial pressure of mass 43 is less than 5 x 10
-10
torr.
When not in use bag and purge with dry (white spot)
nitrogen.
2) Thermal hardware:
TBD
3)
Mechanisms:
TBD
7.2 Optical assembly (telescope/structure)
Follow EIS_CC_Plan NRL April
2000.
7.3 Electronics units
8. OPERATIONS
8.1 The Launch Phase
8.2 After Launch
9. APPENDIX 1. SURFACE CLEANLINESS LEVELS
10. APPENDIX 2. COMPONENT PART CLEANING SCHEDULES
List of cleaning schedules
TYPE OF MATERIAL
|
APPLICABLE SCHEDULE
|
Metal parts in optics bench
|
AA
|
Untreated metal parts
|
A
|
Carbon composite structures
|
A* (see section ***)
|
Alochromed metal parts
|
A
|
Painted metal parts
|
B
|
Electrical/electronic wiring harness
|
TBA
|
Electronics cards
|
G
|
MGSE for optics /optical part supports
|
A
|
Mechanism parts
|
A
|
Lubricated parts
|
H
|
MLI
|
D
|
Mechanical support hardware
|
E
|
Electrical support hardware
|
F
|
Optical components
|
Specialist cleaning only
|
Detector components
|
Specialist cleaning only
|
Motors
|
TBA
|
Elastomers/plastics
|
K
|
Fibre glass units
|
L
|
|
|
Cleaning Schedule AA
Applicable to untreated or
alochromed (but not painted) metal components within the optics
bench.
Preliminary clean (in laboratory or workshop)
1.
Remove visible surface debris, by wipe (e.g. Kimwipes RAL stores cat 33/84900)
and/or vacuum cleaner.
2. Scrub wash with detergent solution, (e.g.
hand cleaner in hot tap water) ensuring that all bolt holes, penetrations,
crevices etc are scrubbed with a non-shedding brush.
For components
containing blind small holes it may be necessary at this stage to wash in an
ultrasonic bath in acetone.
3. Wipe
dry.
Degrease
4. Wash in acetone (isoclean grade - RAL
stores number 14/00180) bath. This procedure to be carried out in ventilated
area or under fume extraction hood.
Use tongs or tweezers. Do not
use gloves for this step.
5. Allow to dry (until visibly
dry).
Clean (in cleaning area, air class at least
10,000)
6. Wash in ultrasonic bath containing approved
detergent solution (e.g. 0.5% of dobonal ethoxylate 91-6 or surfact65 in
demineralised water - at RAL this is 500 cc of detergent in bath filled to
fill level). Wash for 5 minutes then invert part and repeat.
7.
Gloved handling from this point (project approved gloves only).
8.
Flow wash with large quantity of tap water.
9. Flow wash with
demineralised water (analar grade - RAL stores number 14/74490).
10.
Check cleanliness by water break. Loop back to 6 if part fails this
check.
11. Allow to drain.
12. Handle with clean tweezers or
tongs to avoid solvent contact with glove.
13. Flow rinse with
isopropyl alcohol (isoclean grade - RAL stores number 14/02750).
13.
Shake off excess IPA and allow to dry (visibly) under fume hood for up to 10
minutes.
14. Transfer to class 100 flow bench.
15.
Store until ready to progress in clean container - flow bench or Llumalloy bag
or project supplied container.
16. Remove from container. Vacuum bake at
100o C for 8 hours at better than 1x10-5 torr. Record
2-100 amu mass spectrometer bar graph using 10-10 torr pressure
range. Requirement is for mass 43 to be less than 1x10-10 torr and
total outgas rate less than 2x10- 7
torr litre sec-1.
17. Bag in new Llumalloy
bag or project supplied container.
18. Record operation in cleaning
log and part log.
19. Attach "Cleaned component"
tag.
In the event of any procedure error in steps 6-17, loop
back and start again at 6
Cleaning Schedule A
Applicable to untreated or alochromed (but not painted) metal
components.
Preliminary clean (in laboratory or
workshop)
1. Remove visible surface debris, by wipe (e.g. Kimwipes
RAL stores cat 33/84900) and/or vacuum cleaner.
2. Scrub wash with
detergent solution, (e.g. hand cleaner in hot tap water) ensuring that all bolt
holes, penetrations, crevices etc are scrubbed with a non shedding brush. For
components containing blind small holes it may be necessary at this stage to
wash in an ultrasonic bath in acetone.
3. Wipe
dry
Degrease
4. Wash in acetone (isoclean grade - RAL
stores number 14/00180) bath. This procedure to be carried out in ventilated
area or under fume extraction hood. Use tongs or tweezers. Do not use
gloves for this point.
5. Allow to dry (until visibly
dry).
Clean (in cleaning area, air class at least
10,000)
6. Wash in ultrasonic bath containing approved
detergent solution (e.g. 0.5% of dobonal ethoxylate 91-6 in demineralised
water - see schedule AA). Wash for 5 minutes then invert part and
repeat.
7. Gloved handling from this point (project approved gloves
only)
8. Flow wash with large quantity of tap water.
9.
Flow wash with demineralised water (analar grade - RAL stores number
14/74490)
10. Check cleanliness by water break. Loop back to 6
if part fails this check.
11. Allow to drain.
12. Handle
with clean tweezers, tongs to avoid solvent contact with gloved
hands.
13. Flow rinse with isopropyl alcohol (isoclean grade - RAL
stores number 14/02750).
13. Shake off excess IPA and allow to dry
(visibly) under fume hood for up to 10 minutes.
14. Transfer to
class 100 flow bench.
15. Store until ready to progress in
clean container - flow bench or Llumalloy bag or project supplied
container.
16. Remove from container. Vacuum bake at 100oC
for 8 hours at better than 1x10-5 torr. Record 2-100 amu mass
spectrometer bar graph using 10-9 torr pressure range.
17.
Bag in new Llumalloy bag or project supplied container.
18. Record
operation in cleaning log and part log.
19. Attach "Cleaned
component" tag.
In the event of any procedure error in steps
6-17, loop back and start again at 6
Cleaning Schedule B
Applicable to painted
metal structures. This procedure assumes the component has been thoroughly
cleaned by the approved pre-coating procedure prior to painting, e.g. schedule
A, - and has undergone a suitable post painting cleaning by the painting
contractor.
To be carried out in Class 10,000 clean area.
Clean
1. Handle with gloves (Project approved gloves only).
2. Remove
visible surface debris, by dry wipe and/or vacuum cleaner.
3. Carefully
scrub non painted areas by using wipe dampened with isopropyl alcohol,
(isoclean grade stores number 14/02750) ensure that all bolt holes,
penetrations, crevices etc are scrubbed with a brush and that solvent does
not come into contact with paint.
4. Allow to dry (visibly dry) in class
100 clean bench.
Additional (if painted area is seen to be
contaminated) or under project direction
5. Handle with clean tweezers,
tongs or with gloved hands.
6. Check paint tolerance to solvents (contact PA
group).
If appropriate a wipe dampened with isopropyl alcohol (isoclean as 3)
may be used locally. Ensure that solvent does not come into contact with
gloves.
7. Allow to dry (visibly dry) in class 100 clean
bench.
Bake
8. Store in clean container - flow bench or
Llumalloy bag or project supplied container until ready to progress.
9.
Remove from container and vacuum bake at 100oC for 8 hours at better
than 1x10-5 torr. Record 2-100 amu mass spectrometer bar graph on
10-9 torr pressure range.
10. Bag in fresh Llumalloy bag or
project supplied container.
11. Record operation in cleaning log and part
log.
12. Attach "Cleaned component" tag.
In the event of
accidental departures from procedure loop back to step
1.
Cleaning Schedule D - Thermal
Hardware
Applicable to MLI (not ITO coated units).
MLI
will be manufactured in clean down-flow unit from clean materials. It is EIS
policy to clean all subsystems to a known standard where practicable. For MLI a
particular benefit is derived from the vacuum bake as this will greatly reduce
potential contamination from unwanted release agents leached into adhesive
tapes.
Gloves to be worn at all stages and project approved gloves
only.
All stages to take place in at least class 100 clean
area.
Preliminary clean
1. If necessary particles
may be blown off with a gentle flow of filtered white spot dry nitrogen, or
approved vacuum cleaning.
Degrease
2. Degrease should
not be necessary. However if accident recovery requires - small local areas may
be dampened wiped with IPA (isoclean grade RAL stores number 14/02750). Wiping
is to be at absolute minimum as lightly as possible in one direction only. If
marks cannot be removed by this procedure STOP do not try to remove them
- contact thermal control engineer.
3. Allow to
dry.
Clean
4. Store until ready to progress in clean
area.
5. Vacuum bake at 100o C for 72 hours at better than
1x10-5 torr. Record 2-100 amu mass spectrometer bar graph using
10-9 torr pressure range.
6. Store in clean
area.
7. Record operation in cleaning log and part
log.
In the event of accidental departures from procedure loop back
to step 1.
Cleaning Schedule E
Applicable to mechanical
support hardware (not painted) for use in clean rooms.
For units with having
direct contact with optics or optics bench use Schedule
EE.
Preliminary clean (in laboratory or workshop)
1.
Remove visible surface debris, by wipe (e.g. Kimwipes RAL stores cat 33/84900)
and/or vacuum cleaner.
2. Scrub wash with detergent solution, (e.g.
hand cleaner in hot tap water) ensuring that all bolt holes, penetrations,
crevices etc are scrubbed with a non-shedding brush.
3. Flow wash with
tap water to remove detergent, and wipe dry
Degrease
4.
Wipe over using non-shedding wipe dampened with acetone (isoclean grade -
RAL stores number 14/00180). This procedure to be carried out in ventilated
area.
5. Allow to dry (until visibly dry).
Clean (in
cleaning area, air class at least 10,000)
6. Gloved handling from
this point (project approved gloves only).
7. Wipe over using
non-shedding wipes dampened with isopropyl alcohol (isoclean grade - RAL stores
number 14/02750).
8. Allow to dry (visibly).
9. Attach
"Cleaned component" tag.
In the event of accidental
departures from procedure loop back to step at the start of appropriate
section.
Cleaning Schedule EE
Applicable
to mechanical support hardware having direct contact with optics or optics bench
- for use in clean rooms.
For other MGSE use Schedule
E.
Preliminary clean (in laboratory or workshop)
1.
Remove visible surface debris, by wipe (e.g. Kimwipes RAL stores cat 33/84900)
and/or vacuum cleaner.
2. Scrub wash with detergent solution, (e.g.
hand cleaner in hot tap water) ensuring that all bolt holes, penetrations,
crevices etc are scrubbed with a non-shedding brush.
3. Flow wash with
tap water to remove detergent, and wipe dry.
Degrease
4.
Wipe over using non-shedding wipe dampened with acetone (isoclean grade -
RAL stores number 14/00180). This procedure to be carried out in ventilated
area.
5. Allow to dry (until visibly dry).
Clean (in
cleaning area, air class at least 10,000)
6. Wash in ultrasonic
bath containing approved detergent solution (e.g. 0.5% of dobonal
ethoxylate 91-6 in demineralised water - see schedule AA). Wash for 5
minutes then invert part and repeat.
7. Gloved handling from this
point (project approved gloves only).
8. Flow wash with large
quantity of tap water.
9. Flow wash with demineralised water (analar
grade - RAL stores number 14/74490)
10. Check cleanliness by water
break. Loop back to 6 if part fails this check.
11. Allow to
drain.
12. Handle with clean tweezers or tongs to avoid solvent
contact with gloved hands.
13. Flow rinse with isopropyl alcohol
(isoclean grade - RAL stores number 14/02750).
13. Shake off excess
IPA and allow to dry (visibly) under fume hood for up to 10
minutes.
14. Transfer to class 100 flow bench.
15.
Attach "Cleaned component" tag.
In the event of accidental
departures from procedure loop back to step at the start of appropriate
section.
Cleaning Schedule F
Applicable to electrical support
hardware for use in clean rooms. (support hardware cable harness should be
treated under schedule C).
Preliminary clean (in laboratory or
workshop)
1. Remove visible surface debris, by wipe (e.g. Kimwipes
RAL stores cat 33/84900) and vacuum clean paying particular attention to
vents.
2. Remove covers where possible and vacuum clean inner
volume.
Clean (in cleaning area, air class at least
10,000)
3. Gloved handling from this point (project approved
gloves only).
4. Vacuum clean using clean room vacuum
cleaner.
5. Wipe over surface using non-shedding wipes dampened with
isopropyl alcohol (isoclean grade - RAL stores number 14/02750).
6.
Allow to dry (visibly).
7. Attach "Cleaned component"
tag.
In the event of accidental departures from procedure loop
back to step at the start of appropriate section.
Cleaning Schedule G
Applicable to electronics
boards.
Preliminary clean
1. Remove contaminants (flux
etc.) during construction using a non-shedding wipe moistened with isopropyl
alcohol (isoclean grade – RAL stores number 14/02750).
2. Remove
any visible surface debris, by dry nitrogen blow and/or vacuum
cleaner.
Clean (in a least class 10,000 clean area)
3.
Clean in vapour phase plant using arklone F according to SSTD electronics
cleaning procedure (reference TBA).
4. Gloved handling from this point
using project approved gloves.
5. Allow to dry (in class 100 clean
bench). Excess solvent may be blown off using white spot nitrogen.
6.
Store until ready to progress in clean anti static container or bag - e.g.
Lumalloy bag.
7. Vacuum bake (8 hours at 60oC at a pressure
of better than 1x10-5 torr). Record 2-100 amu mass spectrometer bar
graph for 10-9 torr pressure range.
8. Bag in fresh
Lumalloy bag or project supplied container.
9. Record operation in
cleaning log and part log.
10. Attach "Cleaned component "
tag.
In the event of accidental departures from procedure loop back
to step at the start of appropriate section.
Cleaning
Schedule K
Applicable to plastic and elastomer
components.
Preliminary clean (in laboratory or
workshop)
1. Remove visible surface debris, by wipe (e.g. Kimwipes
RAL stores cat 33/84900) and/or vacuum cleaner.
2. Wash with detergent
solution, (e.g. hand cleaner in hand hot tap water) ensuring that all bolt
holes, penetrations, crevices etc are scrubbed with a non-abrasive,
non-shedding brush.
3. Wipe dry
Clean (in cleaning area, air
class at least 10,000)
4. Wash in ultrasonic bath containing
approved detergent solution (e.g. 0.5% of dobonal ethoxylate 91-6
in demineralised water). Wash for 5 minutes then invert part and
repeat.
5. Gloved handling from this point (project approved gloves
only).
6. Flow wash with large quantity of tap water.
7.
Flow wash with demineralised water (analar grade - RAL stores number
14/74490).
8. Allow to drain.
9. Handle with clean tweezers
or tongs and avoid solvent contact with gloved hands.
10. Flow rinse
with isopropyl alcohol (isoclean grade - RAL stores number
14/02750).
11. Shake off excess IPA and allow to dry (visibly) under
fume hood for up to 10 minutes.
12. Transfer to class 100 flow
bench.
13. Store until ready to progress in clean container - flow
bench or Llumalloy bag or project supplied container.
14. Remove from
container. Vacuum bake at 100oC for 8 hours at better than
1x10-5 torr. Record 2-100 amu mass spectrometer bar graph using
10-9 torr pressure range.
15. Bag in new Llumalloy bag or
project supplied container.
16. Record operation in cleaning log and
part log.
17. Attach "Cleaned component" tag.
In
the event of any procedure error in steps 4-15, loop back and start again at
4
Cleaning Schedule LApplicable to fibre glass
components (except electronic cards - see schedule G).
Preliminary
clean (in laboratory or workshop)1. Remove visible surface
debris, by wipe (e.g. Kimwipes RAL stores cat 33/84900) and/or vacuum
cleaner.
2. Wash with isopropyl alcohol (isoclean grade - RAL stores
number 14/02750), ensuring that all bolt holes, penetrations, crevices etc are
scrubbed with a
non-abrasive, non-shedding brush.
3. Wipe
dry.
Clean (in cleaning area, air class at least
10,000)4. Wash in ultrasonic bath containing isopropyl alcohol
(isoclean grade - RAL stores number 14/02750). Wash for 1 minute then invert
part and repeat.
5. Gloved handling from this point (project approved
gloves only)
6. Handle with clean tweezers or tongs and avoid solvent
contact with gloved hands.
7. Shake off excess IPA and allow to dry
(visibly) under fume hood for up to 10 minutes.
8. Transfer to
class 100 flow bench.
9. Store until ready to progress in clean
container - flow bench or Llumalloy bag or project supplied container.
10.
Remove from container. Vacuum bake at 100
oC for 8 hours at
better than 1x10
-5 torr. Record 2-100 amu mass spectrometer bar
graph using 10
-9 torr pressure range.
11. Bag in new
Llumalloy bag or project supplied container.
12. Record operation in
cleaning log and part log.
13. Attach
"Cleaned component"
tag.
In the event of any procedure error in steps 4-11, loop
back and start again at 4
11. APPENDIX 3. GOLDEN RULES FOR CONTAMINATION CONTROL
(with acknowledgement and thanks to Ron Thomas ESTEC)
- Separate optics from all organic and particle sources.
- Keep optical surfaces warm and contamination sources cold.
- Minimise source size and optimise their materials.
- Use vacuum baking to clean up subassemblies.
- Apply purging from critical to less critical volumes.
- Calculate tolerable levels of contamination for both molecular and
particulate contamination.
- Calculate the contributions from all contamination sources.
- Measure the actual acquired contamination throughout the life of the
project.
12. APPENDIX 4. ACRONYM AND ABBREVIATIONS
Acronym Definition
amu atomic mass unit
BU University of
Birmingham
CC contamination control
CCD charge coupled
device
CCIP Contamination Control and Implementation Plan
CDS Coronal
Diagnostic Spectrometer
EGSE electrical ground support
equipment
EIS Extreme-ultraviolet Imaging Spectrometer
ESA European
Space Agency
ESD electro-static
discharge
EUV extreme-ultraviolet
GSE ground support
equipment
IPA isopropyl alcohol
ITO indium tin oxide
MGSE mechanical
ground support equipment
MSSL Mullard Space Science
Laboratory
MLI multilayer insulation
NAOJ National Astronomical
Observatory Japan
NRL Naval Research Laboratory
NVR non-volatile
residue
OM Optical Monitor
PA product assurance
ppm parts per
million
QCM Quartz Crystal Monitor
RAL Rutherford Appleton
Laboratory
SOHO Solar and Heliospheric Laboratory
SSTD Space Science and
technology Department
TBA to be advised
TBC to be confirmed
TBD to
be determined
UV ultra-violet
XMM X-ray Multi-Mirror satellite