Solar
B - EIS
MULLARD SPACE SCIENCE
LABORATORY
UNIVERSITY COLLEGE LONDON
|
Author: A Dibbens
|
SOLAR B - EIS MANAGEMENT
PLAN
Document Number: MSSL/SLB-EIS/AD004.03 02 July
2000
Distribution:
NRL
|
G Doschek
|
|
|
C Korendyke
|
|
|
S Myers
|
|
|
C Brown
|
|
|
K Dere
|
|
|
J Mariska
|
|
|
|
|
NAOJ
|
H Hara
|
|
|
T Watanabe
|
|
|
|
|
RAL
|
J Lang
|
|
|
B Kent
|
|
|
D Pike
|
|
BU
|
C Castelli
|
|
|
S Mahmoud
|
|
Mullard Space Science Laboratory
|
J L Culhane
|
|
|
A Smith
|
|
|
A James
|
|
|
L Harra
|
|
|
A McCalden
|
.
|
|
C McFee
|
|
|
R Chaudery
|
|
|
P Thomas
|
|
|
R Card
|
|
|
W Oliver
|
|
|
P Coker
|
|
|
R Gowen
|
|
|
K Al Janabi
|
|
|
M Whillock
|
|
SLB-EIS Project Office
|
A Dibbens
|
Orig
|
Author:
|
|
Date:
|
|
|
|
|
|
Authorised By
|
|
Date:
|
|
|
|
|
|
Distributed:
|
|
Date:
|
|
Change History
Issue, Date
|
Author
|
Section
|
Changes
|
1.2d, Feb 15 1999
|
M. Whyndham
|
2.2 2.2 3.5
3.11
|
Added contact list . Removed Organigram. Added material in Definition
of System Design and Interface . Added material in Treatment of
Risk.
|
2, July 16, 1999
|
M. Whyndham
|
2.1 2.2
2.3 2.4 2.5 3.1
3.3
3.4 3.5 3.6-3.10 3.11
|
Added actual institutes and WBS Restored Organigram Figure 1 Added
Interface Information Organigram (f. 2) Revised SDT roles Revised Planning
& Reporting Elaborated Archive concepts Table (2) of Models
Added Model Philosophy clarified Removed Requirements management
chart Clarified Requirements concepts Design Critera edited Minor
edits Edits throughout. Reference to future plans Updated
|
3, July 2, 2000
|
A.P. Dibbens
|
All
|
Major revision in most sections to ensure consistency with other
documentation and to remove duplication of information. Addition of Project
Director Addition of Norwegian involvement Update of personnel
assignments
|
1 Introduction
This document is the top level plan for management and systems engineering
for Solar-B EIS (the EUV Imaging Spectrometer).
This plan supersedes the
management plan in the UK proposal. It also covers the activities of non-UK
institutions.
2 Applicable
Documents
RD 1
|
MSSL/SLB-EIS/AD/005
|
Risk Assessment
|
RD 2
|
MSSL/SLB-EIS/PA/001
|
Document List
|
RD 3
|
MSSL/SLB-EIS/PA/002
|
PA Plan
|
RD 4
|
MSSL/SLB-EIS/PA/003
|
Contamination Control Plan
|
RD 5
|
MSSL/SLB-EIS/SP/006
|
EIS Structure Requirements
|
RD 6
|
MSSL/SLB-EIS/SP/007
|
EIS Science Requirements
|
RD 7
|
MSSL/SLB-EIS/SP/001
|
EIS CCD Camera – System Requirements
|
RD 8
|
MSSL/SLB-EIS/SP/008
|
Model Philosophy and Test Plan
|
RD 9
|
MSSL/SLB-EIS/SP/009
|
EGSE Requirements
|
RD 10
|
MSSL/SLB-EIS/SP/011
|
System Definition
|
RD 11
|
MSSL/SLB-EIS/SP/012
|
ICU Design Requirements
|
RD 12
|
MSSL/SLB-EIS/SP/013
|
EIS Mode Definition
|
RD 13
|
MSSL/SLB-EIS/SP/014
|
Specification of Power System
|
RD 14
|
EIS-man-wbs
|
Work Breakdown Structure
|
3 General
Management
3.1 Responsibilities of
Institutions
The institutes who will contribute instrument hardware and/or software for
EIS are:
Mullard Space Science Laboratory (MSSL), University College
London
University of Birmingham (BU)
Rutherford Appleton Laboratory
(RAL)
US Naval Research Laboratory (NRL)
NASA Goddard Space Flight Center
(GSFC)
University of Oslo
PPARC is the UK funding body for this
instrument. NASA is the funding agency for the US teams.
ISAS is the
Japanese body responsible for the Solar-B project.
The general
hardware/software responsibilities of the contributing institutes are indicated
below. The detailed breakdown of responsibilities is indicated in RD
14.
MSSL: Project Management, Systems Engineering, System PA,
Instrument Control Unit, Camera, Harness (internal), Mechanism and Heater
Control Unit (FM), On-board software, EGSE, PM AIV
Birmingham
University: Structure, thermal design, clamshell door, thermal blankets,
MGSE, MTM/TTM AIV
Rutherford Appleton Laboratory: Cleanliness, QCM, FM
AIV
Navel Research Laboratories: Optical elements, filters,
mechanisms, mechanism and heater control unit breadboarding.
Oslo:
support to EGSE software
3.2 Organisation of
Staff
The main chain of responsibility is from ISAS, through the UK Principal
Investigator (PI) to the Project Manager.
An organigram showing
staff roles and reporting lines - mainly within the UK is shown in Figure
1.
In order to formulate the scientific and technical requirements of
the instrument, the PM will work closely with the PI and will attend meetings of
the Science Team.
Points of contact in each Institute for scientific and
technical issues have been nominated as follows:
Institute
|
Local Manager
|
Science Contact
|
Technical Contact
|
MSSL, UCL
|
Tony Dibbens (Ady James from Sep 00)
|
Louise Harra cc. Len Culhane
|
Matthew Whyndham
|
Birmingham University
|
Chris Castelli
|
George Simnett
|
Saad Mahmoud cc Chris Goodall
|
RAL
|
Jim Lang
|
Jim Lang
|
Jim Lang
|
Naval Research Lab
|
Steve Myers
|
George Doschek
|
Clarence Korendyke cc George Doschek
|
NAOJ
|
|
Tetsuya Watanabe cc Hirohisa Hara
|
Hirohisa Hara cc Tetsuya Watanabe
|
ISAS
|
Takeo Kosugi
|
Takeo Kosugi
|
Takeo Kosugi
|
Oslo
|
TBD
|
TBD
|
TBD
|
Cambridge University
|
-
|
Helen Mason
|
-
|
Imperial College
|
-
|
Peter Cargill
|
-
|
St Andrews University
|
-
|
Eric Priest
|
-
|
All science-related correspondence in the project shall be raised with
the UK Project Scientist, Louise Harra, and copied to the UK PI, Len Culhane.
All technical correspondence shall be raised with, or copied to, the Project
Manager (PM). The flow of Solar-B spacecraft interface information is through
the EIS secretariat, Dr. H. Hara at NAOJ. This is shown in Figure
2.
Within the UK a Project Director is responsible to PPARC for
programmatic issues including resources and
scheduling.
Individuals’ email addresses and phone numbers are
shown in the “Contact List”
EIS-man-contacts. Institute
addresses are found in the “Institutes List”
EIS-man-institutes. Several email distribution lists have been
established for Technical and Science topics, see the document “Mailing
Lists”
EIS-man-mlists.
Figure 1. Organigram of
Staff.
Figure
2. Flow of Interface
Information.
3.3 The System Design
Team
The System Design Team (SDT) will have the central role developing the
instrument in response to the requirements. The SDT will include the individuals
named in the technical disciplines shown in figure 1. For institutes other than
MSSL, these represent the points of contact for those institutes. The SDT will
seek advice and information from others from time to time.
The SDT will
hold regular meeting chaired by the PM. The main purpose of these meetings will
be to advance the resolution of technical issues affecting the design and
implementation, including test and calibration of the system. Other functions
are listed (non-exclusively) in Table 1. Minutes of SDT meetings will be made
available to all project participants.
System Design Team Functions
|
Notes
|
System Design
|
Identification and resolution of system-level issues
|
SEMP
|
System Engineering Management Plan, iteration and concurrence
|
WBS
|
Work Breakdown Structure, development and concurrence
|
Requirements
|
Development of system functional requirements, system specifications,
system test requirements and any required subsystem documentation
|
System functional concepts
|
Development of operating concepts
|
Selection of design criteria
|
|
Interface Definition
|
|
Budget Management
|
For items which are subject to budgeting, such as mass, power, alignment,
contamination etc.
|
AIV
|
Assembly, Integration and Verification (including system testing). Plans
and oversight
|
Project Management Activities
|
Detailed Schedules and costing
|
Product Assurance
|
Plans and concurrence
|
Configuration Management
|
Plans and concurrence
|
Reviews
|
|
Risk Management
|
Identification of Risks, Control and Reporting
|
Table 1. Roles of the system design
team.
3.4 Planning and
Reporting
A requirements driven systems engineering process will be employed. This is
manifest in the creation by a document set consisting of:
- Science Requirement
- System Requirements derived from the science requirements
- Subsystem Requirements derived from the system requirements
- Design documents which meet the system requirements
- An Interface Control Document which defines the interfaces to the
spacecraft.
- Integration and test plans which show how the system will be built up and
verified to meet the system requirements
- Calibration plans to show how the system meets the science requirements (as
far as possible prior to launch)
- Commissioning plans to show how the science requirements are validated in
orbit
- PA Plans to indicate how the quality objectives of the system will be met
including cleanliness control
- A user manual to describe the operation of the system which is derived from
the design documents.
The Management of the process will be
governed by:
- A work breakdown structure
- A hierarchy of schedules
- A project budget (separated by funding institute)
- A development plan
- A configuration control plan
- A risk analysis and risk register
- An issues register
While this is not a complete list of
all project documentation it shows the general philosophy adopted.
The
following project meetings will occur. Other, ad-hoc meetings will be
commonplace.
- Minutes of meetings:
- SDT meetings
- Engineering Team Meetings
- MSSL programme review meetings
- Consortium Meetings including engineering meetings
- Design Reviews
- PPARC steering committee meetings
- UK Project Managers Meetings
Meetings of the SDT or
relevant subsets are expected ~monthly on average, but no longer than two months
apart. The meetings follow an agenda :
EIS-meet-sdt-genda. Brief minutes
of these meetings will be made generally available and circulated to the
technical contacts. All significant systems engineering decision-making is done
by or with the agreement of this group, which has representation from all
parties having technical involvement in the instrument. A series of
teleconferences between MSSL and NRL has been established. These are treated in
the same way as SDT meetings. SDT meeting minutes are generally as
EIS-meet-sdt-minutesX, X being the number of the meeting. The
teleconference minutes are filed as
EIS-meet-sdt-tcXXXX, where X is
another serial number.
From time to time, there will be Engineering team
meetings, with similar remit to the SDT, and Consortium Meetings, whose
membership also includes the consortium science team and whose remit therefore
extends to definition of the basic requirements. These meetings will also be
minuted as
EIS-meet-cons-YYMMmins, where YY and MM are the year and
month of the meeting.
At MSSL, a Programme Review Meeting (PRM) is held
on a monthly basis at which the PM will make a report concerning the general
progress of the project, with a particular focus on activities within MSSL.
Other institutes may have similar internal mechanisms. The PM will make his PRM
reports (
EIS-meet-prm-reportX) available.
At intervals (~2 times
per year) there will be a meeting of the PPARC EIS steering committee, to which
each UK participant project manager will make a report and financial statement
and other materials as requested.
The UK Project Director will chair
regular meetings of the UK local managers to review progress and resource
implications.
3.5 Archiving of Project Material
It is intended that a project documentation distribution and archive system
be maintained which:
- allows team members immediate access to up-to-date technical
information
- allows visibility of the dependencies between information (documents)
- shows the configuration status of each item
- allows for historical use of the project material
The term
Archive is used both in the sense of a repository of current material and a
store of historical material. Certain types of electronic document will be
permitted in the archive.
EIS documents will be subject to Configuration Control.
It will be
encouraged that all project documents are made available in electronic form.
The document archive will be propagated from MSSL to other team
institutes, either by network transfer or by other media.
A Document List
is maintained at the MSSL project website.
4 Systems Engineering
Management
4.1 General Approach
In this plan, the term "system" means the EIS instrument. The systems
engineering approach adopted in this project should ensure that there
is:
- Thorough understanding of the system requirements.
- Adequate knowledge and prediction of the system performance.
- Agreement as to the required function and performance of each
subsystem.
- Adequate control of the development of subsystems and systems
interfaces
(to the required performance, on time, under
budget).
The responsibility for systems engineering is held
collectively by the SDT. Additionally, the management techniques should not be
laborious, and therefore the approach to systems engineering is relatively
informal in most areas. However, particular attention is paid to documenting the
needs, requirements and constraints of the system and subsystems.
4.2 Model Philosophy
The Model Philosophy is described in
RD8.
4.3 Design
Reviews
This section will contain details of all the reviews. The following are
scheduled at the time of writing:
- Preliminary design review (PDR)
- Critical design review (CDR)
Other reviews may be required
during the programme. These may include the following:
- Model test reviews
- Flight acceptance review
- Flight readiness review
- Other reviews may be undertaken at subsystem (unit) level, depending on the
criticality of each subsystem.
The US contributions to the
project will be subject to internal NASA reviews which will be attended by EIS
project staff. The outcome of these reviews will be input to the EIS reviews
listed here.
4.4 Evaluation of System
Performance
RD 8 shows how system performance is to be evaluated at various times, give
an outline of full and abbreviated performance tests, and their relationship
with calibration tests.
4.5 Assembly, Integration and Verification (AIV)
Plan
The AIV Plan shows how the instrument will be brought together as a system
from its units, for each of the models which exists as a system. This will
include full references to all the necessary assembly and test procedures. An
important aspect of the system verification is the End-to-End calibration of the
instrument.
4.6 Product Assurance
Plans
The PA plan (RD 3) is based on existing PA plans for other projects. It
includes:
4.7 Treatment of
Risk
It is necessary that the EIS instrument perform in accordance with its
requirements throughout the planned mission and that the development programme
be conducted in a timely and cost effective manner. There is always a finite
probability that the development programme may not result in the delivery of an
instrument that meets its initial requirements (termed "programmatic risk") or
that the instrument may not perform to requirements throughout the mission life
("operational risk"). The programme will be managed to ensure an acceptable
level of each these risks.
The degree to which risks can be reduced
depends broadly on the time and resources available for development in relation
to the requirements. Given that the programme has finite resources and a limited
schedule, the first task must be to ensure that there are no unnecessary
requirements.
The consortium will declare what its attitude to risk will
be in relation to the likely scientific return of the instrument.
Certain
established design criteria may be in conflict with risk reduction - for example
a desire to use innovative technology. These conflicts will be exposed where
they exist and a stance taken at consortium level.
Within the framework
established by time, resources and requirements and attitude to risk, particular
elements of the total risk can be ameliorated in several
ways.
Programmatic risks are first reduced by assessing the system
requirements. Excessive requirements are avoided.
The production
processes of technological items are then studied. Margin in performance may be
included in the specification of subsystems. Where the performance of a
subsystem can deviate from an ideal value a budget for errors will be
calculated, or its quality will be controlled to the required level. This is the
subject of the Product Assurance plans. A means of escaping the consequences of
failures, should they occur, will be sought. The existence of such fall-back
options will be considered for each item where there is an appreciable
development risk. In cases where the risks are high such options will be
actively developed.
Management of operational risks demand the following
types of responses: avoidance of hazardous conditions (processes, materials,
operational procedures), escape from consequences of failure (e.g. by
redundancy), management of degradation (by monitoring of
condition).
Assessment of programmatic and operational risks will be a
function of the Project Manager/Systems Engineer and the System Design Team, and
will result in a series (at various stages during the life of the project) of
system-level risk analyses.
The document Risk Analysis (RD 1) list and
qualifies the existing risks to the development of operation of the EIS
instrument both at system level and at subsystem level. Reference may be
made to sub-system level risk analyses - these are prepared by the responsible
groups.
Each risk source will have an “owner”, whose task it
is to manage that risk, i.e. make quantitative assessment, suggest mitigation,
provide evidence of achievement of quality etc. The ownership of each risk is
stated in the Risk Analysis.
A Risk Register will be maintained following
the PDR.
An Issues Register will be maintained following the PDR